Tuesday, 16 April 2013

15th Tee Update

The stone carpet (drainage layer) is now complete. Before the Rootzone is added to the tee, work moved onto laying the base of the new path and moving the old tees irrigation valve assembly.






2-3 inch Stone carpet layer complete. The edges of the tee are built up to contain it.



Path edging installed



This trench is for a new pipeline to serve irrigation to the new tee.



Digging out to move the old tee valve assembly off the new path.


No comments:

Post a Comment